Saturday, 14 July 2007

Week 19: Wrapped up and locked down

Progress in the last two weeks has been great in spite of the awful weather we've been having. We've not got doors, insulation, electric wiring, skylight (on the back), more fancy joinery on the front. Oh yes, mustn't forget the solar panels and plumbing!



Hmm, me thinks this is not the front door I ordered!

Week 18: no report

The house has been locked down and we've been locked out so no report this week. It was too cold and wet to just admire the view. Hopefully more news next week.

Sunday, 1 July 2007

Week 17: still exposed

It's been foul weather again in the last week which is still getting into the house through the door openings. Doors are arriving though (well two on the front) which make a big difference so pressure is on to get the house locked down and water tight.

At last the turrets have their roofs that brings another perspective to the symmetry of the house. Hopefully the bull nose veranda roofs will be on in the coming week which will also make a big difference.

Working on this site is not for the fainthearted!

Monday, 25 June 2007

Week 16: windows at last

Most of the windows have been installed this week and hopefully the doors will come soon. It's really transformed the outside already. More importantly I think it's going to transform the temperature for Chris and the team to be working on site as they face the bitter winds of winter.

Same weekly view but with windows
First fix in action

Views to the back through the new windows

The back door, well not quite but some windows though!


Sunday, 17 June 2007

Week 15: more verandas

More fiddly bits this week. Verandas to the side and front with more base boards. Weather boards now almost complete and whispering that the windows are due imminently!



Check out the mud. Luckily the drains were back filled in the nick of time.

Saturday, 9 June 2007

Week 14: working on more detail

It's been a bit chillier and windier for the boys up on site this week but they continue to make good progress. Front veranda frame up, complete with bullnose roof profile. Base boards installed under decking, weatherboard and decorative soffits under the roof all represent steady progress on this four day week. Drainage has also been installed which has made a lovely mess of the site (please, please hope it doesn't rain before they fill the trenches back in!).

The benchmark view of the front of the house.

Close up on the front veranda - look for base boards, weatherboard and soffits on the roof line!
Close up on the front entrance, complete with weatherboard

Yes, the drains!

Monday, 4 June 2007

Week 13: boarding up against the weather

Another good build week behind Chris and the team. The main roof is on, just the fiddly bits to do now. Every day feels like a race against the weather so good to see the weather board being put up!


Close up on construction!

A new view of the back garden (complete with gorse and native bush).